financial viability

jigs1980

New member
<h1>Financial Viability</h1>​


A proposal to extend the ABC Gas Company Ltds gas distribution network to the NOIDA industrial cluster, about 40 km east of Delhi, at distance of about 20 kms from the ABC’s existing transmission line, is under the consideration of its CEO, Prerna Goyal. the NOIDA industrial cluster is dominated by the textiles industry including texturising, weaving ,spinning and yarn units with over 2,500 small and medium size units. The potential of gas consumption in these industries is mainly on account of captive power. Power constitutes 40 -65 percent of the production cost in the key target sectors for gas supply. The units in the cluster have been considering reduction of power costs by moving away from the expensive grid supply to captive power generation. The total estimated potential of captive power presently is 45 MW which corresponds to 0.30 million standard cubic meters per day (MSCMD) of gas. The proposed project is essentially an extension of the distribution network in the existing Delhi distribution zone.

A market survey of potential customer to assess the gas demand potential in the region has identified over 40 customers with a combined gas demand of 0.25 MSCMD for captive power. Negotiation for gas supply has also been initiated with them. ABC Gas Ltd has received expression of interest for over 0.075 MSCMD. However, timing of gas supply is the key since alternative fuel option such as solid and liquid fuels and wind energy are available. The expression of interest would fall through if gas is not supplied by mid 2008.
Amit Kumar, an engineer consultant, is hired by Prerna Goyal to identify the most feasible and economical route for laying down the gas pipeline. A preliminary site survey is followed by reconnaissance survey by Amit. After conducting Quantified Risk Assessment and evaluating several pipeline options, the consultant has proposed a 12 inch, 150 class low pressure (19 bar) pipeline for a total length of 30 kms from the ABC’s transmission pipeline. The capacity of the proposed pipeline will be 0.75 MSCMD.
The base investment/capital expenditure is estimated to be Rs 24 crore consisting of the following heads:
i) Engineering Rs 0.50 crore
ii) Project clearance Rs 1.2 crore
iii) Material costs Rs 13.2 crore
iv) Contacts Rs 7.7 crore
v) Commissioning Rs 0.10 crore and
vi) Contingency and insurance Rs 1.3 crore.
The pipe line has an expected life of 10 years.
The other parameters of the projects have been identified by the consultant as listed below
1) Volumes build up (in MSCMD)
YEAR VOLUME YEAR VOLUME
1 0.075 6 0.121
2 0.083 7 0.133
3 0.091 8 0.146
4 0.100 9 0.161
5 0.11 10 0.177
2) Sales price of Gas, Rs 8.90 per standard cubic meter (SCM) with an increase of 3% every year.
3) Purchase price of Gas Rs. 7 per SCM with an increase of 3 % every year.
4) Variable costs are assume to be constant throughout the 10 year life of the pipeline @ Rs. 28 lakhs per annum (Consisting of pigging of pipeline, Rs. 20 lakhs ; cathodic protection of pipeline, Rs. 2 lakh, supervision cost, Rs. 3 lakh; pipeline surveys Rs. 2 lakh; and electricity charges Rs. 1 lakh).
Assuming a straight line method of depreciation of material cost of initial capital investment for tax purposes and 12% required rate of return, analyze as a financial consultant, the financial viability of the proposal and make a recommendation to the CEO of the ABC Gas Limited.
 
Last edited by a moderator:

rosemarry2

MP Guru
<h1>Financial Viability</h1>​


A proposal to extend the ABC Gas Company Ltds gas distribution network to the NOIDA industrial cluster, about 40 km east of Delhi, at distance of about 20 kms from the ABC’s existing transmission line, is under the consideration of its CEO, Prerna Goyal. the NOIDA industrial cluster is dominated by the textiles industry including texturising, weaving ,spinning and yarn units with over 2,500 small and medium size units. The potential of gas consumption in these industries is mainly on account of captive power. Power constitutes 40 -65 percent of the production cost in the key target sectors for gas supply. The units in the cluster have been considering reduction of power costs by moving away from the expensive grid supply to captive power generation. The total estimated potential of captive power presently is 45 MW which corresponds to 0.30 million standard cubic meters per day (MSCMD) of gas. The proposed project is essentially an extension of the distribution network in the existing Delhi distribution zone.

A market survey of potential customer to assess the gas demand potential in the region has identified over 40 customers with a combined gas demand of 0.25 MSCMD for captive power. Negotiation for gas supply has also been initiated with them. ABC Gas Ltd has received expression of interest for over 0.075 MSCMD. However, timing of gas supply is the key since alternative fuel option such as solid and liquid fuels and wind energy are available. The expression of interest would fall through if gas is not supplied by mid 2008.
Amit Kumar, an engineer consultant, is hired by Prerna Goyal to identify the most feasible and economical route for laying down the gas pipeline. A preliminary site survey is followed by reconnaissance survey by Amit. After conducting Quantified Risk Assessment and evaluating several pipeline options, the consultant has proposed a 12 inch, 150 class low pressure (19 bar) pipeline for a total length of 30 kms from the ABC’s transmission pipeline. The capacity of the proposed pipeline will be 0.75 MSCMD.
The base investment/capital expenditure is estimated to be Rs 24 crore consisting of the following heads:
i) Engineering Rs 0.50 crore
ii) Project clearance Rs 1.2 crore
iii) Material costs Rs 13.2 crore
iv) Contacts Rs 7.7 crore
v) Commissioning Rs 0.10 crore and
vi) Contingency and insurance Rs 1.3 crore.
The pipe line has an expected life of 10 years.
The other parameters of the projects have been identified by the consultant as listed below
1) Volumes build up (in MSCMD)
YEAR VOLUME YEAR VOLUME
1 0.075 6 0.121
2 0.083 7 0.133
3 0.091 8 0.146
4 0.100 9 0.161
5 0.11 10 0.177
2) Sales price of Gas, Rs 8.90 per standard cubic meter (SCM) with an increase of 3% every year.
3) Purchase price of Gas Rs. 7 per SCM with an increase of 3 % every year.
4) Variable costs are assume to be constant throughout the 10 year life of the pipeline @ Rs. 28 lakhs per annum (Consisting of pigging of pipeline, Rs. 20 lakhs ; cathodic protection of pipeline, Rs. 2 lakh, supervision cost, Rs. 3 lakh; pipeline surveys Rs. 2 lakh; and electricity charges Rs. 1 lakh).
Assuming a straight line method of depreciation of material cost of initial capital investment for tax purposes and 12% required rate of return, analyze as a financial consultant, the financial viability of the proposal and make a recommendation to the CEO of the ABC Gas Limited.

Hello mate,

Please check attachment for ebook on Financial Viability and Sustainability, so please download and check it.
 

Attachments

  • ebook on Financial Viability and Sustainability.pdf
    399.2 KB · Views: 0
Top